By Sean Jones
When it comes to revenue recognition for construction contractors, one of the more technical and frequently misunderstood areas is the accounting for uninstalled materials. How these costs are treated can significantly affect the timing of revenue recognition and the profitability reported on long-term contracts.
What Are Uninstalled Materials?
Uninstalled materials are goods purchased or produced for a specific contract that have not yet been installed or incorporated into the project.
A critical factor to consider is who controls the materials at the point they are procured:
- If the customer controls the materials and the materials are specific to the contract, the contractor may apply the rules of ASC 606 – Revenue from Contracts with Customers, as detailed below.
- If the contractor retains control and the materials can be redirected to another job, the items should be treated as contractor inventory on the balance sheet. No revenue is recognized until installation or further performance by the contractor occurs.
Accounting Treatment When the Customer Controls Uninstalled Materials
Many construction contractors recognize revenue over time using a cost-to-cost input method (percentage of completion). ASC 606 provides specific guidance for situations where large material purchases occur before related installation work.
Because significant material purchases may not reflect actual project progress, ASC 606 requires careful evaluation to avoid overstating project completion.
According to ASC 606:
- If significant materials are purchased but have not been installed and purchasing them does not reflect progress toward satisfying the performance obligation, the costs must be excluded from the measure of progress (i.e., removed from “costs incurred to date” in the POC calculation).
- The contractor recognizes revenue equal to the cost of those materials, with no profit margin, until the materials are installed or otherwise contribute to progress on the specified contract.
Why This Matters
Improperly accounting for uninstalled materials can distort key financial metrics. It may result in:
- Overstated revenue and gross profit
- Inaccurate WIP schedules
- Misalignment between accounting and project management reports
- Potential issues with bonding companies, lenders, and auditors
Best Practices for Contractors
-
- Identify uninstalled materials early – Maintain clear and timely tracking of material purchases.
- Separate uninstalled material costs – Use distinct cost codes to differentiate installed vs. uninstalled materials.
- Coordinate across teams – Ensure project managers and accounting staff communicate about delivery, storage, and installation timing.
- Review contract terms – Determine when control of materials passes—many contracts explicitly address ownership of pre-installed materials.
- Document key judgments – Revenue recognition decisions should be well-supported
In Summary
Under ASC 606, contractors should recognize revenue for uninstalled materials (when these materials are controlled by the customer) only to the extent of cost, with no associated profit, and exclude those costs from the progress measurement until installation occurs.
This treatment aligns revenue recognition with actual performance and provides a more accurate financial picture.
Contact Sean Jones, Miller Cooper Principal from our Construction group with any questions.